NAO report into the Green Deal and Energy Company Obligation
On 14 April 2016, The National Audit Office (NAO) published Green Deal and Energy Company Obligation, a report assessing the value for money of the Green Deal and Energy Company Obligation (ECO) schemes.
The Green Deal created a mechanism for funding energy efficiency improvements in which, instead of paying up-front to have energy efficiency measures installed in a property, the cost was funded by long-term savings on electricity bills. On 23 July 2015, Climate Change Secretary Amber Rudd announced there would be no further funding to the Green Deal Finance Company and that the Government would stop any future funding releases of the Green Deal Home Improvement Fund.
The ECO provides support for the installation of energy efficiency measures to reduce energy consumption and to help people living in fuel poverty and in properties that are hard to treat.
The NAO report is a damning one, concluding that the Green Deal did not achieve value for money, that it cost taxpayers £240 million,and that it had not generated any additional energy savings. This, it suggested was because the Department of Energy and Climate Change (DECC)'s design and implementation of the scheme failed to persuade householders that energy efficiency measures were worth paying for. Only 1% of the measures installed through the schemes were funded with a Green Deal loan.
It also found that whilst energy suppliers had met their ECO obligations for saving carbon dioxide and reducing bills, the design of the scheme to support the Green Deal had added to the costs of meeting those obligations, which had reduced the value for money of the ECO. However, they were unable to determine by how much.
Although the target of improving 1 million homes with the schemes had been achieved, NAO suggested that this was not a direct indicator of progress against the objective of reducing carbon dioxide emissions because of the different amounts of CO2 saved by different types of energy-efficiency measures.
In addition, because the schemes had initially focussed on harder-to-treat homes, they had saved substantially less CO2 than previous supplier obligations. The projected 24 megatonnes of CO2 savings are only around 30% of what the previous schemes achieved.
The overall cost per tonne of carbon saved by the schemes (excluding energy suppliers’ administrative costs) was £94, compared with £34 for the previous set of schemes.
A second report into DECC’s loans to the Green Deal Finance Company was also published. This found that DECC expected it would not recover its £25 million stakeholder loan to the finance company, or £6 million of interest. Demand for Green Deal finance was lower than the Department forecast from the outset, and so the finance company could not cover its operating costs. The Department does however expect to recover a second loan in full.
Amyas Morse, Head of the NAO, said, “Improving household energy efficiency is central to government achieving its aims of providing taxpayers with secure, affordable and sustainable energy. The Department of Energy and Climate Change’s ambitious aim to encourage households to pay for measures looked good on paper, as it would have reduced the financial burden of improvements on all energy consumers. But in practice, its Green Deal design not only failed to deliver any meaningful benefit, it increased suppliers’ costs – and therefore energy bills – in meeting their obligations through the ECO scheme. The Department now needs to be more realistic about consumers’ and suppliers’ motivations when designing schemes in future to ensure it achieves its aims.”
[edit] Related articles on Designing Buildings Wiki
- Carbon emissions reduction target.
- Energy Act.
- Energy certificates.
- Energy company obligation.
- Energy performance contracts.
- Feed in tariff.
- Free schools.
- Fuel poverty.
- Green Deal Home Improvement Fund.
- Green Deal scrapped.
- Green Deal.
- Renewable heat incentive.
- Zero carbon homes.
- Zero carbon non domestic buildings.
Featured articles and news
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.






















Comments
Lessons from UK Green Deal compared to the US Better Buildings Neighborhood Program (BBNP) show that financial incentives alone to householders don't increase participation. Other forms of support to householders are needed as well. The design of the Green Deal had fundamental flaws.
SOURCE: "Lessons for the UK Green Deal from the US BBNP" by Aaron Gillich, Minna Sunikka-Blank and Andy Ford. Building Research & Information. 2016.